FORAN- McIlvenna Bay

Project Phases

Feasibility Study & Detailed Engineering

Date

2023-2025

Client

FORAN Mining/GMining Services

Location

Saskatchewan, Canada

Conventional Copper/ Zinc Flotation plant, with dewatered filter cake as a concentrate product to be
hauled to 3rd party by truck. Consideration for zero discharge to environment, therefore tailings are
processed in a conventional paste plant facility and injected underground into the mine workings.
Compressed project schedule, leveraging multi-discipline tandem engineering/ construction approach.

- Prior to Detailed Engineering kick-off, led layout of a feasibility study optimization activity with full
process plant 3D model and CAPEX update as deliverable
- Responsible for production of FS 3D model, 2D GA’s, all calculations related to containment of spill
scenarios, pumpbox and tankage live volume, and distribution box/ launder capacity.
- Responsible for conceptual design of all platework items during FS Phase